Wednesday, 11 April 2012

Concrete piers done and formwork started

Concrete piers were poured and they had started the formwork for the concrete slab.



Garage side

Garage Back

Portico

Sitting room

Sitting room and hot water heater

Hot water heater



Drop edge beam


Looks like an old concrete well




Left hand side of outdoor room

Right hand side of outdoor room

Not sure why this is needed in the rumpus room? 
My guess is that it's for the drop edge beam.





Water tank

Outdoor room

Rumpus room

Top soil scraped for the shed slab









No comments:

Post a Comment

Note: only a member of this blog may post a comment.