Building Timeline


Construction

26/02/2012 Demolition started
06/03/2012 Demolition complete
06/03/2012 Sewer Encasement complete
03/04/2012 Site scrape complete
05/04/2012 Piers complete, form work started
09/04/2012 Banana trees planted
14/04/2012 Slab complete
22/04/2012 External drainage started
25/04/2012 External drainage complete
27/04/2012 Frames delivered
28/04/2012 Ground floor framing started
01/05/2012 Fisrt floor framing started
03/05/2012 Frame completed
05/05/2012 Windows installed, internal plumbing started
10/05/2012 Ground floor Hebel installation started
29/05/2012 Scaffolding installed
11/06/2012 First floor gutters, fascia and roof tiles complete
24/06/2012 Rendering almost complete
01/07/2012 First floor eaves and render painting complete
10/07/2012 Ground floor roof tiling and electrical cabling complete
18/07/2012 Independent Frame Inspection
21/07/2012 Ceiling, wall and acoustic insulation installed
23/07/2012 Gyprock started
28/07/2012 Gyprock complete
31/07/2012 Internal fit out started
08/08/2012 Kitchen and vanity cabinetry installation started
16/08/2012 Tiling started
01/09/2012 Ceaserstone installed
08/09/2012 Internal painting started
16/09/2012 Power pole installed